Installation

Installation

Determine the main load-bearing area on the mounting frame, and try to keep the position of the slewing drive distributors of bearing raceway quenching soft belt ("S" mark) at an angle of 90° to the main load-bearing area.

The horizontal rotation of the rotary transmission mechanism is placed on the mounting bracket to ensure that the transmission mechanism is in contact with the surface of the installation without gaps. If there is a gap, the material that can fill the gap should be filled to prevent deformation of the transmission mechanism after the bolt is tightened.

When installing the connecting bolt, connect the box to the mounting bracket, and then connect the gear/turbine to the rotating part. Tightening the mounting bolt should be symmetric in the 180° direction. The mounting bolts should have sufficient preload force, and the preload force on the bolts should be between 0.6 and 0.7 times the yield point of the bolts.

The following table is the recommended table for bolt tightening torque:

Bolt diameter

10

12

14

16

18

20

22

24

27

30

33

Torque(N.m)

69

117

185

280

390

560

750

960

1400

1900

2600


After installation, the debris inside and outside the mechanism should be removed in time to ensure that there is no interference with other components during operation. Welding work on or near equipment where this product is installed is not permitted. After the installation is completed, run the slewing mechanism under no-load condition, observe whether the operation is flexible and unblocked, and then run the test under load. Check the installation bolts after running test to see if there is looseness of the heavy slewing drive.

Lubricating
Improper lubrication is the most common cause of failure of the slewing mechanism. Therefore, the lubrication interval must be carried out regularly. Depending on the frequency of use and external working conditions, the type of grease used before and after replacement should be consistent to ensure compatibility. After long-term lag or cleaning of the slewing mechanism, the grease must be injected for the first time.

The following table lists the lubrication cycle of the product under different working conditions for reference.

Working conditions

Lubrication cycle

Dry and plot occasions (rotary table, machine)

300 hours or 6 months of work

Outdoor environment (crane, excavator, etc.)

200 hours or 6 months of work

Harsh environment (mountain, ocean, desert, etc.)

150 hours or4 months of work

Extreme conditions (mining, copper, etc.)

50 hours or2 months of work